[3110.2014] Meter Station Rehab Group 1 (MS10_0B only)
Project Title: |
[3110.2014] Meter Station Rehab Group 1 (MS10_0B only) |
Design Firm: |
Kimley-Horn and Associates Inc. |
Bid Advertisement: |
November 2020 |
Bid Opening: |
December 2020 |
Location: |
CRWS - Dallas/Euless/Carrollton |
Estimated Construction Cost in Millions: |
1 to 5 |
Description of Work: |
Replacement of compound meter station MS 10_0B. |
Invitation to Bid: |
Not Available |
Lowest Bidder: |
Not Available |
Bid Award: |
Not Available |
[3110.2046C] 09BC-1 - Phase 2
Project Title: |
[3110.2046C] 09BC-1 - Phase 2 |
Design Firm: |
Plummer Associates Inc. |
Bid Advertisement: |
January 2021 |
Bid Opening: |
February 2021 |
Location: |
CRWS - Grapevine |
Estimated Construction Cost in Millions: |
5 to 10 |
Description of Work: |
Installation of 8900 LF of 48-inch relief pipeline. Phase 2 is the most upstream of segment of the 09BC-1 interceptor. |
Invitation to Bid: |
Not Available |
Lowest Bidder: |
Not Available |
Bid Award: |
Not Available |
[3110.2053B] Effluent Filters Phase IIIB Improvements
Project Title: |
[3110.2053B] Effluent Filters Phase IIIB Improvements |
Design Firm: |
Plummer Associates Inc. |
Bid Advertisement: |
September 2020 |
Bid Opening: |
October 2020 |
Location: |
CRWS - Treatment Plant |
Estimated Construction Cost in Millions: |
15 to 20 |
Description of Work: |
This project includes the next phase of conversion of sand filters into cloth media filters. Filters #1 #2 #13 and #14 will be converted to cloth media for the additional hydraulic throughput and high effluent quality that result from that media. The remaining sand filters will be decommissioned. |
Invitation to Bid: |
Not Available |
Lowest Bidder: |
Not Available |
Bid Award: |
Not Available |
[3110.2130] Bear Creek Interceptor Relief Phase 1 (Downstream)
Project Title: |
[3110.2130] Bear Creek Interceptor Relief Phase 1 (Downstream) |
Design Firm: |
Lockwood Andrews & Newnam Inc. |
Bid Advertisement: |
March 2021 |
Bid Opening: |
April 2021 |
Location: |
CRWS - Grand Prairie |
Estimated Construction Cost in Millions: |
over 25 |
Description of Work: |
Replacement of parallel 54- and 84-inch unlined reinforced concrete pipe with a single non-corrosive interceptor along Bear Creek from Hunter Ferrell Road to IH-30. Phase 1 includes 8840 LF of 84- to 96-inch interceptor four siphons and the replacement of meter stations MS1_0B and MS2_0B. The Bear Creek Interceptor converges with the West Fork Interceptor at the downstream limits of Phase 1 improvements. The project limits were amended to include 5000 LF of 110-inch realignment of the West Fork Interceptor Segment WF-G following an emergency repair of the pipeline due to slope embankment failure in March 2020. |
Invitation to Bid: |
Not Available |
Lowest Bidder: |
Not Available |
Bid Award: |
Not Available |
[3173.400] Mountain Creek Interceptor Rehab Segment 30MC-1
Project Title: |
[3173.400] Mountain Creek Interceptor Rehab Segment 30MC-1 |
Design Firm: |
Carollo Engineers |
Bid Advertisement: |
November 2020 |
Bid Opening: |
December 2020 |
Location: |
CRWS - Mountain Creek - Grand Prairie/Dallas |
Estimated Construction Cost in Millions: |
15 to 20 |
Description of Work: |
This project includes 7000 linear feet of 90-inch gravity relief interceptor to replace existing 54- and 78-inch diameter unlined reinforced concrete pipelines that are in poor condition due to corrosion. The new pipeline is to be installed in the same alignment as the existing 54-inch interceptor. |
Invitation to Bid: |
Not Available |
Lowest Bidder: |
Not Available |
Bid Award: |
Not Available |
[3828.644] 25HC-3 Henrietta Creek Relief Interceptor
Project Title: |
[3828.644] 25HC-3 Henrietta Creek Relief Interceptor |
Design Firm: |
Carollo Engineers |
Bid Advertisement: |
January 2021 |
Bid Opening: |
February 2021 |
Location: |
DCRWS - Fort Worth |
Estimated Construction Cost in Millions: |
15 to 20 |
Description of Work: |
This project consists of approximately 12900 LF of 48- to 54-inch diameter gravity pipeline to relieve the existing 24-inch interceptor. Improvements also include a major highway crossing at IH-35W and the elimination of existing aerial crossings by lowering the profile of the system. |
Invitation to Bid: |
Not Available |
Lowest Bidder: |
Not Available |
Bid Award: |
Not Available |
[3828.645] 25HC-4 / 25HC-5 Henrietta Creek Relief Interceptor
Project Title: |
[3828.645] 25HC-4 / 25HC-5 Henrietta Creek Relief Interceptor |
Design Firm: |
Teague Nall & Perkins Inc. |
Bid Advertisement: |
January 2022 |
Bid Opening: |
February 2022 |
Location: |
DCRWS - Fort Worth/Haslet |
Estimated Construction Cost in Millions: |
10 to 15 |
Description of Work: |
This project consists of approximately 12850 LF of 36- to 48-inch diameter gravity pipeline and the replacement of Meter Station 10_0HC. Meter Station Haslet (MS_HAS) is to be designed by others and incorporated into the Authority's construction of 25HC-4/25HC-5 per Interlocal Agreement with the City of Haslet. |
Invitation to Bid: |
Not Available |
Lowest Bidder: |
Not Available |
Bid Award: |
Not Available |
[3828.2038] Influent Coarse Screen Improvements-DCRWS
Project Title: |
[3828.2038] Influent Coarse Screen Improvements-DCRWS |
Design Firm: |
Freese And Nichols Inc. |
Bid Advertisement: |
September 2020 |
Bid Opening: |
October 2020 |
Location: |
DCRWS - Treatment Plant |
Estimated Construction Cost in Millions: |
1 to 5 |
Description of Work: |
This project consists of installing coarse screens ahead of fine screens in two channels along with associated electrical and instrumentation. The driveway access for hauling dumpsters will be improved upon as well. |
Invitation to Bid: |
Not Available |
Lowest Bidder: |
Not Available |
Bid Award: |
Not Available |
[3510.2020] MCRWS Plant Expansion to 4.5 MGD
Project Title: |
[3510.2020] MCRWS Plant Expansion to 4.5 MGD |
Design Firm: |
Garver LLC |
Bid Advertisement: |
November 2020 |
Bid Opening: |
December 2020 |
Location: |
MCRWS - Midlothian - Treatment Plant |
Estimated Construction Cost in Millions: |
10 to 15 |
Description of Work: |
This project includes expanding the MCRWS Plant from an average day capacity of 3.0 MGD to 4.5 MGD. |
Invitation to Bid: |
Not Available |
Lowest Bidder: |
Not Available |
Bid Award: |
Not Available |
[3826.2009A] Red Oak Creek Interceptor Rehabilitation Segment 40RO-1 Phase 2
Project Title: |
[3826.2009A] Red Oak Creek Interceptor Rehabilitation Segment 40RO-1 Phase 2 |
Design Firm: |
Jacobs Engineering |
Bid Advertisement: |
November 2020 |
Bid Opening: |
December 2020 |
Location: |
ROCRWS - Red Oak |
Estimated Construction Cost in Millions: |
5 to 10 |
Description of Work: |
This project consists of approximately 6815 linear feet (LF) of 48-inch diameter gravity relief interceptor to replace the existing 27- to 30-inch unlined reinforced concrete pipeline (RCP) and the replacement of meter station MSRO2_0. The 40RO-1 project was split into two construction phases. Phase 1 which includes the replacement of a 760 LF segment of 30-inch diameter unlined RCP is being constructed with the RBC-1 & RBC-2 Gravity Outfall Project (refer to 3826.2023). This most downstream segment was expedited due to the critical condition of the pipeline and its impact to the operation of the treatment plant. Phase 2 will include the remaining 6055 LF of condition and capacity improvements to the existing RCP interceptor. |
Invitation to Bid: |
Not Available |
Lowest Bidder: |
Not Available |
Bid Award: |
Not Available |
[3826.2008] Red Oak Creek Interceptor Rehabilitation Segment 40RO-2
Project Title: |
[3826.2008] Red Oak Creek Interceptor Rehabilitation Segment 40RO-2 |
Design Firm: |
Not Available |
Bid Advertisement: |
March 2022 |
Bid Opening: |
April 2022 |
Location: |
ROCRWS - Red Oak |
Estimated Construction Cost in Millions: |
15 to 20 |
Description of Work: |
This project consists of a new gravity relief interceptor to replace 9765 LF of 27-inch unlined reinforced concrete pipe or vitrified clay pipe. The preliminary design report completed in 2018 identified several segments that have an expected remaining useful life of less than five years due to corrosion. The existing pipe is also undersized and unable to convey the projected wastewater flows. |
Invitation to Bid: |
Not Available |
Lowest Bidder: |
Not Available |
Bid Award: |
Not Available |
[3826.2030] Red Oak Creek Relief Interceptor Segment 40RO-3
Project Title: |
[3826.2030] Red Oak Creek Relief Interceptor Segment 40RO-3 |
Design Firm: |
Not Available |
Bid Advertisement: |
January 2021 |
Bid Opening: |
February 2021 |
Location: |
ROCRWS - Red Oak |
Estimated Construction Cost in Millions: |
1 to 5 |
Description of Work: |
Construction of 1640 linear feet of 18-inch parallel relief interceptor to replace an existing 10-inch PVC pipe. |
Invitation to Bid: |
Not Available |
Lowest Bidder: |
Not Available |
Bid Award: |
Not Available |
[3826.906] Red Oak Creek Relief Interceptor Segment RO-3
Project Title: |
[3826.906] Red Oak Creek Relief Interceptor Segment RO-3 |
Design Firm: |
Dunaway Associates LP |
Bid Advertisement: |
March 2021 |
Bid Opening: |
April 2021 |
Location: |
ROCRWS - Red Oak |
Estimated Construction Cost in Millions: |
1 to 5 |
Description of Work: |
This project consists of approximately 8720 LF of 27- to 30-inch gravity relief interceptor to replace an 18- to 21-inch unlined reinforced concrete pipe interceptor. The existing pipe is undersized for the projected wastewater flows. RO-3 is a commitment in the Sanitary Sewer Overflow Initiative Agreement with TCEQ. |
Invitation to Bid: |
Not Available |
Lowest Bidder: |
Not Available |
Bid Award: |
Not Available |
[7002.2018B] Murphy Drive GST No. 4 Rehabilitation
Project Title: |
[7002.2018B] Murphy Drive GST No. 4 Rehabilitation |
Design Firm: |
Jones & Carter Inc. |
Bid Advertisement: |
July 2020 |
Bid Opening: |
August 2020 |
Location: |
TCWSP - Murphy Drive Pump Station |
Estimated Construction Cost in Millions: |
1 to 5 |
Description of Work: |
Project consists of rehabilitation of interior and exterior of Ground Storage Tank (GST) No. 4 including recoating roof repairs and ladder replacement. |
Invitation to Bid: |
Not Available |
Lowest Bidder: |
Not Available |
Bid Award: |
Not Available |
[7002.2003] Filter Media and Underdrain Replacement
Project Title: |
[7002.2003] Filter Media and Underdrain Replacement |
Design Firm: |
Hazen and Sawyer |
Bid Advertisement: |
July 2021 |
Bid Opening: |
August 2021 |
Location: |
TCWSP - Treatment Plant |
Estimated Construction Cost in Millions: |
5 to 10 |
Description of Work: |
Project includes replacement of the media and underdrains for all 24 existing filters filter valves and actuators filter hydraulic study and recommended filter improvements. |
Invitation to Bid: |
Not Available |
Lowest Bidder: |
Not Available |
Bid Award: |
Not Available |
[7002.2083] Chlorine Contact Basin and Mixing Chamber
Project Title: |
[7002.2083] Chlorine Contact Basin and Mixing Chamber |
Design Firm: |
Hazen and Sawyer |
Bid Advertisement: |
November 2020 |
Bid Opening: |
December 2020 |
Location: |
TCWSP - Treatment Plant |
Estimated Construction Cost in Millions: |
1 to 5 |
Description of Work: |
The addition of a free chlorine contact basin that would include an ammonia and fluoride mixing chamber to prevent uneven distribution of ammonia and fluoride to the clearwells. |
Invitation to Bid: |
Not Available |
Lowest Bidder: |
Not Available |
Bid Award: |
Not Available |
[3210.2051A] 11-40TM-2 PH 1
Project Title: |
[3210.2051A] 11-40TM-2 PH 1 |
Design Firm: |
Teague Nall & Perkins Inc. |
Bid Advertisement: |
July 2022 |
Bid Opening: |
August 2022 |
Location: |
TMCRWS - Lancaster/Cedar Hill |
Estimated Construction Cost in Millions: |
10 to 15 |
Description of Work: |
This project consists of approximately 17650 LF. of 45- to 72-inch diameter gravity parallel relief interceptor. The project also includes the replacement of the Lancaster Meter Station (MS_LAN). This project is the downstream segment of the overall project. |
Invitation to Bid: |
Not Available |
Lowest Bidder: |
Not Available |
Bid Award: |
Not Available |
[3210.2066C] Plant Rehabilitation A
Project Title: |
[3210.2066C] Plant Rehabilitation A |
Design Firm: |
AECOM Technology Corp |
Bid Advertisement: |
March 2021 |
Bid Opening: |
April 2021 |
Location: |
TMCRWS - Lancaster/Cedar Hill |
Estimated Construction Cost in Millions: |
10 to 15 |
Description of Work: |
Project includes installation of cranes at Return Activated Sludge Pump Station No. 1 along with isolation valve and check valve replacements on the influent and discharge side of the pumps lighting improvements to the west part of the plant replacement of the mechanism of Primary Clarifier No. 1 gate replacement at Division Box 2 and 2A planting of cedar trees along southern and western property lines replacement of the roof insulation and lighting at the Maintenance Building addition of a wind screen and cover at Grit 3 replacement of actuators at the Screening Facility replacement of perforated fine screen panels on Screen 1 and 2 chains and debris rakes. The Arc flash SKM model will be updated as part of this project as well. The air quality in the Sludge Dewatering Facility will be addressed during this project. The improvements will improve employee safety and minimize hydrogen sulfide effects on electrical and electronic equipment. |
Invitation to Bid: |
Not Available |
Lowest Bidder: |
Not Available |
Bid Award: |
Not Available |
[3210.2076A] Meter Station Rehabilitation (MS_BB/ MS_CH/ MS_FER)
Project Title: |
[3210.2076A] Meter Station Rehabilitation (MS_BB/ MS_CH/ MS_FER) |
Design Firm: |
BGE Inc. |
Bid Advertisement: |
July 2021 |
Bid Opening: |
August 2021 |
Location: |
TMCRWS - Lancaster/Cedar Hill |
Estimated Construction Cost in Millions: |
1 to 5 |
Description of Work: |
Replace meter stations MS_BB MS_CH and MS_FER in the Ten Mile Creek Interceptor System. |
Invitation to Bid: |
Not Available |
Lowest Bidder: |
Not Available |
Bid Award: |
Not Available |
[3210.681A] TM-1 Relief Interceptor Phase I
Project Title: |
[3210.681A] TM-1 Relief Interceptor Phase I |
Design Firm: |
HDR Engineering Inc. |
Bid Advertisement: |
January 2021 |
Bid Opening: |
February 2021 |
Location: |
TMCRWS - Lancaster/Cedar Hill |
Estimated Construction Cost in Millions: |
15 to 20 |
Description of Work: |
TM-1 Phase I improvements include 5000 LF of 72-inch interceptor along Ten Mile Creek in Lancaster from Riverway Drive to Blue Grove Road. |
Invitation to Bid: |
Not Available |
Lowest Bidder: |
Not Available |
Bid Award: |
Not Available |
[3210.2090] Effluent Outfall Relocation
Project Title: |
[3210.2090] Effluent Outfall Relocation |
Design Firm: |
Halff Associates Inc. |
Bid Advertisement: |
March 2021 |
Bid Opening: |
April 2021 |
Location: |
TMCRWS - Lancaster/Cedar Hill |
Estimated Construction Cost in Millions: |
1 to 5 |
Description of Work: |
Relocation of the TMCRWS effluent outfall structure to approximately 600 linear feet downstream of current location in Ten Mile Creek. Scope also includes support services to acquire an amendment to the discharge permit for the relocation of the outfall. |
Invitation to Bid: |
Not Available |
Lowest Bidder: |
Not Available |
Bid Award: |
Not Available |
[3410.2002/3410.2003] Walker-Calloway Phases 2 & 3
Project Title: |
[3410.2002/3410.2003] Walker-Calloway Phases 2 & 3 |
Design Firm: |
RJN Group Inc. |
Bid Advertisement: |
January 2021 |
Bid Opening: |
February 2021 |
Location: |
W-C - Fort Worth/Hurst |
Estimated Construction Cost in Millions: |
1 to 5 |
Description of Work: |
Phase 2 includes the rehabilitation of 1986 linear feet of existing 42-inch pipeline. Phase 3 includes the rehabilitation of 4500 LF of existing 27- and 30-inch unlined RCP along Walker Branch and Calloway Branch at the convergence of the two interceptor systems. The Calloway Branch segment includes 2300 LF of 27-inch pipe beginning at the upstream end of Phase 2 north of Hurst Boulevard and continues along Calloway Branch to Melbourne Road while the Walker Branch segment includes 1200 LF of 30-inch unlined RCP along State Highway 10. |
Invitation to Bid: |
Not Available |
Lowest Bidder: |
Not Available |
Bid Award: |
Not Available |